Bellevue Gold is set to deliver its forecasted increase in ore grades following the resumption of development at its Deacon North development in Western Australia.
The company is now on track to start ore production from Deacon North in the June 2026 quarter.
Bellevue Gold said a dedicated development jumbo returned to the Deacon North area after development activity was completed at the Armand mining area.
The initial focus of this jumbo is to complete the Deacon North decline and return air drive in order to develop key capital infrastructure. Independent firing has been established for this development and is being utilised to improve development rates.
Grade control drilling for Deacon North is also underway, with results expected to be reported as more drilling is completed.
Bellevue is relying on the growing contribution of ore from Deacon Mean, Viago and Decon North to drive its increase in production forecast through fiscal 2026.
Meanwhile, Bellevue appointed Shaun Hackett as chief geologist. Hackett is a highly experienced and respected resource geologist and previously worked in lead roles at Snowden Mining consultants and Xstract mining consultants.
He will commence work in January 2026 at the same time as incoming COO Peter Ganza.
Hackett will replace Sam Brooks, who will leave the company to pursue other opportunities.
In addition, Bellevue is on track to reach its aim of being the most renewably powered off-grid mine in Australia.
The company reported 101 hours of 100 per cent instantaneous renewable energy at its power station, operating the mine and processing plant with engines off during this period.
The company expects to see higher contributions from the solar farm and wind farm, which will reduce the use of diesel and LNG in the power station.
The company’s renewable energy penetration is now at the upper end of the targeted renewable energy penetration rate of 80 per cent to 90 per cent.