Capricorn Metals Ltd. has completed construction of its Karlawinda Expansion Project (KEP) on schedule, achieving the targeted steady-state throughput of 6.5 million tonnes per annum.
The company confirmed that continuous ore processing has commenced through the plant’s new parallel crushing, milling, and carbon-in-leach (CIL) circuits.
Following a 12-month build delivered by Capricorn’s internal construction team alongside key industry contractors, site commissioning was completed over the last two weeks.
All components of the new processing infrastructure are now operational. The expanded facility is currently processing low-grade ore and will transition to run-of-mine (ROM) grade ore over the coming week as operations reach steady-state capacity.
The completed expansion is fully integrated into the broader Karlawinda gold project, with operational focus shifting toward fine-tuning product sizing from the KEP crushing circuit.
Commissioning of the CIL infrastructure and pipework for the second tailings storage facility (TSF 2) is also finished, while ROM ore stockpiles continue to build on ROM Pad 2.
With the expansion now active, Karlawinda is projected to produce approximately 150,000 ounces of gold annually. Production remains backed by an estimated mine life of more than a decade based on current ore reserves.
“The commencement of continuous ore processing at the Karlawinda Expansion Project on schedule is a significant milestone for Capricorn,” said Capricorn Executive Chairman Mark Clark.
“It is the culmination of a huge effort from our construction and operations teams, supported by key contractors.
“We now look forward to the transition of Karlawinda into a long-life operation producing around 150,000 ounces of gold per annum.”