Rio Tinto will restart idled production capacity at New Zealand’s Tiwai Point aluminium smelter after signing a three-and-a-half-year, 50-megawatt electricity contract with Contact Energy.
The bridging agreement will supply predominantly renewable energy to bring Line 4 back online.
Once operational, the line is expected to boost output by roughly 30,000 tonnes annually, restoring the facility to its full capacity of 360,000 tonnes per year and lifting Rio Tinto’s combined Australasian smelting capacity by 3 per cent.
At current global spot prices, the extra production could generate about NZ$100 million (AU$82.58 million) in additional annual export revenue for New Zealand.
Rio Tinto Aluminium Pacific Operations Managing Director Armando Torres said the deal underscores the company’s commitment to its New Zealand assets amid surging global appetite for low-carbon metal.
“The restart of Line 4 will increase aluminium production at a time when demand for high quality, low carbon aluminium has never been higher,” Torres said.
Preparations and commissioning are scheduled to begin in October 2027, with full production targeted for December 2027.
To safeguard New Zealand’s broader energy security during peak demand periods, power supply under the contract will scale back to 25 megawatts over the winter months.
Line 4 has sat idle since April 2020, initially shuttered due to COVID-19 pandemic market disruptions and prolonged uncertainty over the smelter’s future. Rio Tinto has since locked in multi-decade power supply agreements for the broader site.
New Zealand Aluminium Smelters General Manager Michelle Henderson welcomed the milestone as a major boost for Southland and the national economy.
She noted the bridging contract enables an early restart while both companies negotiate a long-term power purchase agreement that could keep Line 4 operating for at least another two decades.