The share of global mining projects that progressed to their next stage of development has decreased from 3.8 per cent in the final quarter of 2019 to 2.8 per cent in the first quarter of 2020, and momentum is expected to slow further in Q2 2020 due to the coronavirus outbreak, according to GlobalData.
Vinneth Bajaj, Mining Analyst at GlobalData, said with several countries entering complete lockdown, mining companies have minimised their workforce to temporarily suspend operations and development activities.
“As of April 13, the progress of 35 mines currently under construction globally was disrupted due to such lockdowns. These projects account for around 9 per cent of total mines under construction and around 10.5 per cent of total capacity as measured by run-of-mine (ROM).”
Anglo American slowed the development of its US$5.3bn Quellaveco copper mine in Peru, withdrawing employees and contractors amid the country’s lockdown. The company also temporarily put Woodsmith, its newly acquired potash project in the UK, on hold from 27 March. In Canada, Vale initially placed its Voisey’s Bay mine on care and maintenance for four weeks, but has since extended this for up to three months – delaying the development of its mine expansion project and transition from open pit to underground mining.
Similarly, in Chile, Teck Resources has suspended construction works at its Quebrada Blanca Phase 2 in the wake of the country’s lockdown measures.
On the other hand, the updated feasibility study work of the Prieska copper-zinc project in South Africa is undergoing remotely, with the site being shut-down temporarily.
Bajaj said around 76 mineral projects advanced in the first quarter of 2020, down from the 101 projects in Q4 2019.
“Assets moving forward into construction include the El Pilar copper project in Mexico, the Zaldivar copper-molybdenum in Chile, and North star iron ore in Australia.”