29Metals Ltd. has obtained a regulatory breakthrough towards restarting its suspended Capricorn Copper operations in Queensland, alongside reporting its strongest monthly mining output in more than three years at its Golden Grove asset.
The company confirmed it has received preliminary approval for a major amendment to its Environmental Authority from the Queensland Department of Environment, Tourism, Science and Innovation.
The decision greenlights the construction of Tailings Storage Facility 3 and a new water treatment plant, providing a long-term waste and water management solution for the first time under 29Metals’ ownership. Pending final clearances, 29Metals plans to go to tender for construction in 2027.
Since suspending operations in March 2024, the miner has reduced surface water inventory at Capricorn Copper by 2.3 gigalitres, the equivalent of 900 Olympic swimming pools, bringing levels well below compliance limits.
29Metals remains on track to submit final federal environmental information before the end of 2026, alongside completing its restart definitive feasibility study and evaluating funding options ahead of a final investment decision.
29Metals CEO James Palmer said the approval validates three years of intensive site water management and community engagement.
“This is a big step forward towards FID, as the team work hard to finalise the DFS and complete the evaluation of funding solutions,” Palmer said.
“We remain excited by the potential for Capricorn Copper to more than double 29Metals’ annual copper production.”
Meanwhile, operational momentum at the company’s Golden Grove mine in Western Australia accelerated sharply in October. Ore mined hit 156,000 tonnes, up 50 per cent on the year-to-date average and the highest monthly volume achieved in over three years.
The surge was driven by additional ore sources across Gossan Hill and the safe recommencement of mining at Xantho Extended after a 12-month hiatus.
Following a successful maintenance shutdown in September, the mill operated at an annualised run-rate of 1.6 million tonnes per annum, with first production from Oizon and development ore from Gossan Valley on track before year-end.